L&L has completed their repairs this week and we are pleased with the work done in front of the Magee’s and Kelsay’s, as well as between the Little’s and Lowell’s. The Miller’s had some work done in front of their property, as well. This completes the major repairs to Lakeshore. Thank you for your patience.
Lakeshore Repairs Coming Soon
For those of you who called yesterday and others who are curious, Petty Landscaping is working on the Idell’s drainage to repair the rock wall and re-channel the drainage swale along Lakeshore. Work should be completed today.
In the next few weeks (depending on continued dry weather) L&L Asphalt should be able to complete the work on Lakeshore which will repair the damage done by heavy rains. They will unclog the culvert between the Links and the Idells (18981 and 18948 Lakeshore) in front of the Kelsays (19355 ), the Magees (19043) and the failing valley gutter between the Lowells and Littles (19053 and 19065) where L&L will do additional work for the homeowners replacing the wooden flume with a concrete version with curbed sides. For more detail on the work approved, 2016_L&L-Asphalt_Estimates.If you would like additional work done (on your driveway, for instance), now would be a good time to contact David Lockridge at L&L (903.561.2887).
ODAW: Oxygen for Lake #3
Your Dues At Work: Lake #3 had an issue with low oxygen levels, particularly during the dog days of summer. Wayne Tiller did the research and found an aerator system which will not only replenish oxygen, but cut down on thermal stratification, reduce “muck” accumulation on the bottom, improve water clarity, improve fish production and reduce surface film. The system has been placed so that it will the maximum gallons per minute.